POWERGRID ER NER Transmission Limited

Acq Date :  
Date of Incorporation :  
Under Implementation
TBCB Subsidiaries
Annual Report -
Financial Statements -
 ERNER.pdf (1.9 MB)
Director List

Scope

1) Creation of 220kV GIS bus at Banka (POWERGRID) S/s

2) 400kV bus extension works at Banka (PGCIL) 400/132kV Substation

3) 400/220kV, 2x500MVA
     ICTs along with associated bays (220kV bays in GIS and 400kV bays in AIS)

4) 2 nos. of 220kV GIS line bays at Banka (POWERGRID) for termination of Banka (POWERGRID)–
    Goradih (Sabour New) 220kV D/C line of BSPTCL
       Future provision: Space for future 220kV GIS bays: 6 no.

5) Upgradation of existing 132kV Namsai (POWERGRID) S/s to 220kV (with 220kV side as GIS)

6) Kathalguri (NEEPCO) – Namsai (POWERGRID) 220kV D/c line

7) Extension at Kathalguri (NEEPCO) switchyard: 2 nos. of GIS line bays for termination of Kathalguri
    (NEEPCO) – Namsai