POWERGRID Bhadla Transmission Limited
Acq Date :
Date of Incorporation :
Financial Statements -
Director List
Under Implementation
TBCB Subsidiaries
Annual Report - PBTL_1.pdf (25.6 MB)
Audit_Report_and_Financials_PBTL.pdf (1.5 MB)
Formerly known as Fatehgarh Bhadla Transco Limited.
Petition under Sections 63 and 79 of the Electricity Act, 2003 read with Articles 11 and 12 of the Transmission Service Agreement dated 11.11.2020 (TSA) seeking condonation of time overrun & consequent extension of Schedule COD and relief for cost overrun & consequential increase in annual non-escalable transmission charges on account of Force Majeure and Change in Law events pertaining to POWERGRID Bhadla Transmission Limited (PBTL)
- 1x240 MVAr Switchable line reactor for each circuit at each end of Fatehgarh-II – Bhadla- II 765 kV D/c line (2nd) 240 MVAr
- 765 kV reactor- 4 (2 reactors each at Fatehgarh-II and Bhadla-II) Switching equipment for 765 kV reactor - 4 (2 Switching equipment each at Fatehgarh-II and Bhadla-II)